Overview:

Built in 2014, this greenfield project was designed to transport and store clean oil from 13-18-26-18W3 oil battery to the 13-12-30-22W3 Tank Farm. The pipeline allows up to 15000 bbls/day of oil to be transported from the Plato area of into a Kindersley oil gathering system. 

Facility Specifications:

Transports Viking oil production.

Ownership Interest:

60% working interest in mainline and storage

100% working interest in connecting lateral

Associated Pipeline:

57.2 kms of pipeline in total.